Scaffold and Crane removal at Peloton Avenue

Dear Neighbours

Re: Chobham Manor, Stratford – Scaffold Removal Peloton Avenue and Mobile Crane

We are writing to you to inform you that from 23 October it will be necessary to close one lane of Peloton Avenue to allow for the removal of some of the scaffold from Phase 2-A.

This work will not affect any parking or access but a scaffold trailer will be parked alongside the hoarding in Peloton Avenue near to Honour Lee Avenue. During this time, there will be construction vehicles working in the area. We apologise for any inconvenience but we shall ensure that regular road sweeping takes place to remove any debris created.

On Wednesday 31 October we are expecting to start removing the final tower crane on 2-A, to allow us to do this we will be siting a mobile crane on Peloton Avenue, this will not interfere with any parking spaces and will have a traffic marshal in attendance to ensure safety.

The work will take place during normal site working hours 07.45-18.00 We apologise for the inconvenience this may cause and will ensure that all working areas are kept clean, tidy and secure.

We trust this information is useful and if you have any questions please contact Matthew Aylen, Regeneration Performance Manager by email at matt.aylen@taylorwimpey.com. If you are interested in finding out more about the Chobham Manor site please visit our websites:

www.chobhammanor.co.uk   www.chobhamlife.co.uk

 

letter to residents: 22nd Oct – scaffold and crane removal

Complete our community survey…

We are keen to capture your feedback towards the development of Chobham Manor’s community facility and commercial units. Your feedback will help shape the way in which services and activities are provided to serve your local community.

Please take the time to complete the community survey using the following link: https://www.surveymonkey.co.uk/r/TQ538RQ

It should take no more than 5-10 minutes to complete and the survey will close on 2 November 2018.

 

Thank you,

Chobham Manor Team

Second hand sale of children’s items

Second hand sale of children’s clothes, toys, books and maternity clothes

 

Date: Saturday 17 November 2018,

Time: 10am – 12noon

Place: Timber Lodge Café, Queen Elizabeth Olympic Park, 1A Honour Lea Ave, London E20 1DY

 

Organised by Chobham Manor Residents

 

A perfect opportunity to look through your family’s wardrobes and drawers for unwanted and quality items and to find bargains in good time for Christmas.

 

  • For more information and if you wish to sell your items, please reserve your table by Thursday 1 November 2018 by emailing events@cme20.com
  • Tables will be allocated on a first come, first served basis. Spaces are limited, so please register early!
  • We also welcome donations of relevant items on the day. Any proceeds from donated items will go to The Magpie Project (a charity providing a safe and fun place for mums and children under five in temporary or insecure accommodation in Newham)
  • Please ensure all items intended for sale or donation are clean and in good condition.

 

Second Hand Sale flyer

Stratford and West Ham October Newsletter

Newham’s Stratford and West Ham October 2018 Newsletter

You can download the newsletter here Stratford and West Ham Community Neighbourhood’s October 2018  Newsletter

If you would like to submit a listing or story, please email CN.Stratfordwestham@newham.gov.uk

 

Construction works 2A and 2BCD

Crane at Peloton Avenue

Dear Neighbours

Re: Chobham Manor, Stratford – Crane lifting Peloton Avenue

We are writing to you to inform you that from 16th October 2018 it will be necessary to close part of Peloton Avenue to allow pre-cast flooring to be lifted in to place on 2B-D.

Unfortunately, for health and safety assurance it will be necessary for parking spaces 4,5 6 and 7 to be suspended to allow for the work to take place this will be until Friday 19th October. Alternative parking is available in any unmarked parking bay, this has been agreed with the parking control company.

The work is going to involve the closure of one lane on Peloton Avenue while the work takes place.  A full traffic management plan will be in place to ensure pedestrian and vehicular safety.

The work will take place during normal site working hours 08.30-16.30 and for health and safety reasons all work carried out will be separated from the public using Heras fencing.

We apologise for the inconvenience this may cause and will ensure that all working areas are kept clean, tidy and secure.

We trust this information is useful and if you have any questions please contact Matthew Aylen, Regeneration Performance Manager by email at matt.aylen@taylorwimpey.com. If you are interested in finding out more about the Chobham Manor site please visit our websites:

www.chobhammanor.co.uk             www.chobhamlife.co.uk

 

Letter posted to residents can be found here: Precast work Peloton 16Oct

Works have started on Phase 3

Dear Residents,

Re: Chobham Manor, Stratford – Development Phase 3-A and Phase 3-E

We are writing to give you a quick update on work that is taking place across Chobham Manor.

We have now started on the third phase of the build, this phase is split into 5 separate sub phases; Phase 3-A, 3-B, 3-C, 3-D and 3-E, see drawings below:

Initially we will be working in sub phases 3-A and 3-E there will be 105 properties in 3-A and 32 Properties in 3-E which also contains a community facility and a Nursery. The enabling works for the piling is taking place with the expectation of the pre-boring to have commenced on the 24 September and the piling to commence following that. We are again working with our environmental consultants to ensure the work causes the least amount of disruption possible.

Whilst work is taking place there will be site managers on site monitoring the noise, vibration and air quality sensors to ensure we do not exceed the set limits.

The piling will not take place outside of the agreed working hours 8.30am – 5pm Monday to Friday, Chobham Manor site will ensure that this is adhered to.

We trust this information is useful and if you have any questions then please contact Matthew Aylen, Regeneration Performance Manager by email at: matt.aylen@taylorwimpey.com or the 24/7 Park hotline on 0800 0722 110.

If you are interested in finding out more about the site please visit our websites:

www.chobhammanor.co.uk

 

Kind regards,

 

Matthew Aylen

Regeneration Performance Manager

Taylor Wimpey

 

Note: the following information has been posted to residents:

Residents Letter piling Phase 3A and 3E water Sept2018