Abercrombie Road Closed on 11/04/2019.

Dear Residents,

Re: Abercrombie Road Closed on 11/04/2019

In order to complete the urgent work taking place on phase 2, it will be necessary to close Abercrombie road between Peloton avenue and Derny avenue on 11th April 2019.  The work will take place during normal site working hours 08.00-18.00 We apologise for the inconvenience this may cause and will ensure that all working areas are kept clean, tidy and secure.

We trust this information is useful and if you have any questions please contact Matthew Aylen, Regeneration Performance Manager by email at matt.aylen@taylorwimpey.com. If you are interested in finding out more about the Chobham Manor site please visit our websites

www.chobhammanor.co.uk   and   www.chobhamlife.co.uk

Regards

Your estate management team.

Mobile Crane Placement Peloton Avenue

Dear Residents,

Re: Chobham Manor, Stratford –Mobile Crane Placement Peloton Avenue

We are writing to you to inform you that on 9th April it will be necessary to close Peloton Avenue at the junction of Abercrombie Road and also Villiers Gardens to allow the placement of a Mobile Crane. Pedestrian access will not be affected.

This work may affect access to your parking bays and if this is the case we have arranged for alternative parking to be available in the Velodrome Carpark the alternative parking arrangements will be for 4th April 2019 between 08.00-18.00. I will need your registration number to pass on to Velodrome to organise by Monday Morning.

The work will take place during normal site working hours 08.00-18.00 We apologise for the inconvenience this may cause and will ensure that all working areas are kept clean, tidy and secure.

We trust this information is useful and if you have any questions please contact Matthew Aylen, Regeneration Performance Manager by email at matt.aylen@taylorwimpey.com.

Weekend Construction Work On Sunday’s From 31th March 2019.

Dear Residents,

Please be advised there will be weekend construction work taking place every weekend between Saturday 30th March till Sunday 30th June. The work will focus on Chobham manor phase 2B, 2C and 2D. Working hours will consist of:

Saturday 13:00 – 17:00

Sunday 08:30 – 13:30

Apologies for the inconvenience this may cause some resident.

Kind Regards

Your Estate Management Team.

Weekend Construction Work On Saturday’s From 30th March.

Dear Residents,

Please be advised there will be weekend construction work taking place every weekend between Saturday 30th March till Sunday 30th June. The work will focus on Chobham manor phase 2B, 2C and 2D. Working hours will consist of:

Saturday 13:00 – 17:00

Sunday 08:30 – 13:30

Apologies for the inconvenience this may cause some resident.

Kind Regards

Your Estate Management Team.

Crane removal on Friday 29th March 2019.

Evening Surgeries with your property manager and apprentice property manager.

Hello Residents,

Please come along to our open house surgeries hosted by your property manager giving you a chance to meet face to face and discuss ways your estate management team can help.

Many Thanks
Estate Management Team

CMRA Open Meeting